Network Rack Implementation

Qualification Questions

Is Rip And Replace Existing Patch Cables Required? If So, How Many Switches?
Is Cable Management Required? If So, How Many Network Closets?
Is Full Port Documentation Required? If So, How Many Switches?
Is Patch Cable Labeling Required? If So, How Many Switches?
Is Misc Cable Management Hardware Required? If So, How Many Switches?
Is Site Survey + Port Planning Required?
Is Network Closet Refresh Remove Equipment From Rack Required? If So, How Many Devices?
Is Network Rack Install Required? If So, How Many Racks?
Is Rack Network Equipment Required? If So, How Many Devices?
Is Punch Down To Patch Panel Required? If So, How Many Cables?
Is Mount And Configure Ups Required? If So, How Many Ups?
Is Add On Ups Install And Configure Remote Management Card Required? If So, How Many Units?

Example Project Plan

Implementation
  • Remove And Replace Each Cable In The Switch And Patch Panel
  • Feed Cables Through Customer Provided Cable Management
  • Organize And Velcro Cable Bundles Together
Validation
  • Fill Out Patch Panel To Switch Port Spreadsheet
Closing
  • Provide Port Documentation To Customer
Discovery
  • Site Survey
Planning
  • Port Planning